Implementation plan · BuildLedger ERP

Phased rollout & go-live

Migrating from QuickBooks · 14-week plan · delivered with Gulf Implementation Partners

Timeline
14 wks
Milestones
2/5 done
Open risks
2
Partner
Gulf Implementation Partners
Phased rollout
  1. Discovery & chart-of-accounts mappingWk 1–2

    Mapped QuickBooks GL to BuildLedger schema; signed off by finance.

  2. Environment & SSO/SCIM setupWk 3–4

    UAE region provisioned; Microsoft 365 SSO + SCIM provisioning live.

  3. Data migration & parallel runWk 5–9

    Migrating 6 yrs of GL history; one parallel close cycle in progress.

    45%
  4. Workflow & dashboard rebuildWk 10–12

    Rebuild 12 workflows + 6 dashboards; UAT with project controllers.

  5. Cutover & go-liveWk 13–14

    Final cutover, hypercare, decommission QuickBooks.